QMF Construction was awarded the contract by Pensar Construction Group to upgrade and construct new pits at the Alexandra Hills Reservoir site in the Redland City Shire. This was on behalf of SEQ water.

 

Scope of works on this project included, but was not limited to:

  • Construction of flowmeter pits to 3 areas
  • Construction of Valve pits to 2 areas

Other aspects of this project included; working within a residential and school area, this meant construction activities had to be minimised during school drop off and pick up. Working within a restricted area, working within strict timelines to minimise impact on supply network.

Works completed: Early September 2016

Project Contact: Troy Elder – Pensar Construction Group

http://www.seqwater.com.au/latest-updates/works/2016/05/10/minor-capital-works-alexandra-hills-reservoirs-%E2%80%93-may-august-2016