QMF Construction was awarded the contract by Gongues Constructions to construct a pump station and retention tank at Gosford in the Central Coast Region.

Scope of works on this project included but was not limited to:

  • Design, supply, installation and certification of formwork to tanks and valve pit
  • Placement and fixing of steel reinforcement to tanks and pits
  • Placement and finishing of concrete to tanks and pits

Other aspects included working at heights, access constraints, working with radius formwork, working within environmental controls, working within a confined space.

Works completed May 2016

Project contact: Aladino Domingues – Gongues Constructions

http://www.gosford.nsw.gov.au/environment-and-waste/water-and-sewer